Breach of contract: FG gives ultimatum to Chinese firm

Published

on

Spread The News

The Minister of Transportation, Rotimi Amaechi, has accused the China Civil Engineering Construction Corporation of breaching a railway contract after the delivery date passed without delivery of the ordered coaches.

 

The contract was signed in December 2017 and was supposed to expire in February 2019. However, the delivery date has since elapsed.

 

Amaechi made the statement during a visit to China where he led a delegation to inspect the pace of work at the CRRC.

 

Nigeria had requested for the production of 64 coaches which are to be deployed on the Abuja-Kaduna and Lagos-Ibadan rail lines.

 

“The pace of construction is slow and they need to improve on it. In fact, the contract has expired; we may not have paid all the money but we paid quite a substantial sum and, therefore, they should construct speedily.

ALSO READ: What ails Chris Ngige?

“The contract was signed in December 2017 and was supposed to expire in February 2019. The time has expired and there is a breach of contract but we will look at what the law says because more than one third of the money has been paid.”

 

Amaechi gave a new directive, stating the deadline for the deployment of ten coaches out of the 64 coaches should not be more than June this year. He said ten coaches were requested first to improve on the Kaduna-Abuja line.

 

Amaechi said a verbal agreement was made with CCECC to establish a factory that will be used to manufacture coaches and wagon in Nigeria in order to create job opportunities for Nigerians.

 

He also disclosed that the Chinese firm opted for Ogun State as the location for the factory despite Amaechi favouring Zaria.

 

Meanwhile, the Nigerian Railway Corporation has been informed by Amaechi to provide land for the wagon factory to CCECC before May 8, 2019.