Ikeja Electric customers to experience outage from Oct. 11
Ikeja Electric Plc says some areas under its operational network will experience outages for a period of eight weeks to enable the Transmission Company of Nigeria (TCN) to re-conduct its 132KV lines.
The National Daily reports that Mr. Olajide Kumapayi, Chief Technical Officer, Ikeja Electric, made the announcement at a news briefing on Monday in Ikeja.
Kumapayi said the project which would begin on Oct. 11 was aimed at increasing the capacity of the transmission lines to wheel more power from the generation companies.
He noted that some of 132Klines installed over 50 years ago had become obsolete and degraded due to time and usage.
According to him, areas that will be affected by this stage of the project include Oregun, Police Training College, Oba Akran, Oke Ira, Ogba, Magodo, Anifowoshe, and Omole Phase One.
Kumapayi said: “The TCN is currently embarking on the upgrade of the 132KV lines from Ikeja West to Ota and Alimosho in stages. This is the second stage.
“The TCN is replacing all the aluminum conductors with gap conductors which are more sophisticated to withstand heat and have more capacity to carry current.
“The implication of this is that from 8 a.m. to 6 p.m. every day, the substations controlling these areas will be switched off which will affect the feeders connected to them.
“This will affect all categories of customers within the area especially our Maximum Demand (MD) customers such as Ikeja City Mall, Police College, Lagos State University Teaching Hospital and the Ikeja High Court.”
He added that the TCN would also move to Alimosho and Agege axis during the next stage.
Kumapayi noted that the upgrade was a power sector initiative to boost the transmission and distribution of electricity to Nigerians.
Also, Mr. Felix Ofulue, Head, Corporate Communications, Ikeja Electric, said the DisCo had written to the MD customers notifying them of the situation.
Ofulue said the company was also meeting with its bilateral power supply agreement partners and appealed to all those affected to exercise patience with the DisCo during the period.
“Even though this is a TCN project, it is our duty to inform our customers of the situation because we are the ones that interface with them on a daily basis.
“We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our system to improve power supply to customers under our network,” Ofulue said.
-
Comments and Issues3 days agoCan President Tinubu Revive Nigeria’s Moribund Refineries?
-
Business3 days agoTinubu knocks Atiku’s subsidy plan, says proposal shows ‘ignorance’ of economy
-
Entertainment5 days agoPoco Lee faces rape allegation as unverified UK arrest report spreads online
-
Latest6 days agoTinubu files: US Judge grants four-day extension in FOIA disclosure battle
-
Featured6 days agoBeyond Osun 2026: What Adeleke’s re-election reveals about Nigeria’s road to 2027
-
Business3 days agoTikTok, ByteDance agree to $400m settlement in US children’s privacy case
-
Business6 days agoStandard Bank eyes stake in OPay ahead of planned $4bn US IPO
-
Featured3 days agoEconomic Reality vs Party Machinery: What will drive Nigeria’s 2027 election?