Residents of Lekki, some parts of Victoria Island, Agungi, Chevron, Badore, and other areas on the island part of Lagos, are set to experience blackout as the Transmission Company of Nigeria (TCN) plans to carry out maintenance work in Ajah substation from September 7, 2022, to September 9, 2022, for a period of 12 hours daily.
The maintenance work also includes the relocation of Egbin/Aja 330kV transmission line 3 to a spare Omotosho 330kV line 2 bay as well as the repair of gas leakage on one of the isolators in the substation.
This disclosure is contained in a statement issued on Tuesday, September 6, 2022, by the General Manager, Public Affairs of TCN, Ndidi Mbah, saying that the power outage will occur between 7 am and 7 pm daily.
Mbah said that during this period, Aja, Lekki transmission stations, and the Alagbon/Aja 330kV transmission line would be out of service, to ensure a safe workspace for the engineers, adding that Alagbon transmission substation would receive power through the Ijora/Alagbon 132kV transmission line.
READ ALSO: Ikeja Electric speaks on planned blackout in parts of Lagos
The statement read, “The Transmission Company of Nigeria plans to carry out maintenance work in Aja substation from Wednesday 7th to Friday 9th September 2022, from 7 am to 7 pm daily. This includes the relocation of Egbin/Aja 330kV Line 3 to a spare Omotosho 330kV Line 2 bay as well as the repair of gas leakage on one of the isolators in the substations.
“During this period, Aja, Lekki transmission stations and the Alagbon/Aja 330kV transmission line would be out of service, to ensure safe workspace for the engineers.
“Similarly, the Alagbon transmission substation would receive power supply through the Ijora/Alagbon 132kV transmission line.
“The maintenance work will affect bulk power supply and expectedly cause an outage in Badore, Sangotedo, Jakande, Chevron, Agungi, Lekki and some parts of Victoria Island.
‘’TCN regrets any inconveniences this may cause electricity consumers within the affected areas and assure Nigerians of its determination to continue to deliver bulk power supply to distribution load centers nationwide.”
Meanwhile, the TCN had about 3 days ago confirmed that a fire incident occurred on Saturday, the 3rd of September at its Adiabo 330/132/33KV substation in Cross River State.
It stated that its engineers were working to ensure the restoration of power supply to the affected areas as they were replacing the affected equipment.
-
Sports4 days agoSenegal opens Dakar 2026 Youth Olympic Games, Africa’s first Olympic event
-
Latest7 days agoTinubu endorses Nigeria’s participation in 2026 World Travel Market London
-
Football6 days agoU-17 Women’s World Cup: Flamingos Beat Mexico to Reach Quarter-Finals
-
Business4 days agoNNPC’s N66-per-litre petrol discount set to end October 31
-
Latest4 days agoINEC recognises Pantami for Gombe, keeps Kano NDC candidate off final list
-
Latest4 days agoFG Announces N50,000 cash support for vulnerable Nigerians under new relief programme
-
Latest5 days agoNetanyahu, Eisenkot face coalition deadlock as Israel struggles to form new government
-
Latest4 days agoNDC Chieftain tells Atiku to drop presidential ambition over son’s support for Tinubu