Tinubu set to commission 3 critical gas projects
President Bola Tinubu is set to commission three critical gas infrastructure projects being developed by the Nigerian National Petroleum Company Limited (NNPCL) and partners.
The Special Adviser to the President on Media and Publicity, Ajuri Ngelale, in a statement on Friday, indicated that the projects will support the Federal Government’s effort to grow value from the nation’s gas assets while eliminating gas flaring.
According to the statement, “The delivery of the projects was accelerated from the inception of the administration in keeping with the overall objective of deepening domestic gas supply as a critical enabler for economic prosperity.”
The Special Adviser to the President on Media and Publicity highlighted that the projects lined up for commissioning include the AHL Gas Processing Plant 2 (GPP – 2) – 200mmscf/d, an expansion to the Kwale Gas Processing Plant (GPP – 1), which currently supplies about 130MMscf/d of gas to the domestic market.
The processing plant is designed to process 200MMscf/d of rich gas and deliver lean gas through the OB3 Gas Pipeline.
The plant will also produce about 160,000 MTPA of Propane and 100,000 MTPA of Butane which would reduce the dependency on LPG Imports.
The AHL Gas Plant is being developed by AHL Limited, an incorporated Joint Venture owned by NNPC Limited and SEEPCO.
The second project, the ANOH Gas Processing Plant (AGPC) – 300MMscf/d, is an integrated 300MMscf/d capacity gas processing plant designed to process non-associated gas from the Assa North-Ohaji South field in Imo State.
When completed, the plant will produce dry gas, condensate, and LPG.
The statement further indicated that the gas from ANOH Gas Plant will significantly increase the domestic gas supply, leading to increased power generation and accelerated industrialisation.
The ANOH Gas Plant is being developed by ANOH Gas Processing Company, an incorporated Joint Venture owned by NNPC Limited and Seplat Energy Plc on a 50-50 basis.
Moreover, the ANOH-OB3 CTMS Gas Pipeline Project involves the engineering, procurement, and construction of 36”x23.3km ANOH-OB3 Project.
The Transmission Gas Pipeline will evacuate dry gas from the Assa North-Ohaji South (ANOH) primary treatment facility (PTF) to the OB3 Custody Transfer Metering Station (CTMS) for delivery into the OB3 pipeline system.
About 600MMscf/d is estimated to be available from two separate 2 x 300MMscf/d capacity gas processing production trains from AGPC & SPDC JV.
The projects will increase gas supply to the domestic market by approximately 500mmscf/d, creating a better investment climate and promoting balanced economic growth cumulatively.
-
Business6 days agoNigeria: Whither the fruits of 2026 crude oil windfall?
-
Latest6 days agoMakinde declares 2027 presidential bid under PDP–APM alliance
-
Comments and Issues7 days agoPolitical Parties Primaries: Consensus or Coronation?
-
Comments and Issues6 days agoDoes it matter to Africa if Nigel Farage comes to Number 10?
-
Business5 days agoTrump-Xi summit sparks fresh questions for Nigeria’s economy, tech sector
-
Business4 days agoNigeria’s foreign debt climbs 22% to $51.86bn under Tinubu administration
-
Comments and Issues6 days agoIs France Real or Playing Ping Pong With Africa?
-
Comments and Issues6 days agoThe “Onuku” Called Kenneth Okonkwo