Lekki, parts of V.I, other areas to experience blackout
Residents of Lekki, some parts of Victoria Island, Agungi, Chevron, Badore, and other areas on the island part of Lagos, are set to experience blackout as the Transmission Company of Nigeria (TCN) plans to carry out maintenance work in Ajah substation from September 7, 2022, to September 9, 2022, for a period of 12 hours daily.
The maintenance work also includes the relocation of Egbin/Aja 330kV transmission line 3 to a spare Omotosho 330kV line 2 bay as well as the repair of gas leakage on one of the isolators in the substation.
This disclosure is contained in a statement issued on Tuesday, September 6, 2022, by the General Manager, Public Affairs of TCN, Ndidi Mbah, saying that the power outage will occur between 7 am and 7 pm daily.
Mbah said that during this period, Aja, Lekki transmission stations, and the Alagbon/Aja 330kV transmission line would be out of service, to ensure a safe workspace for the engineers, adding that Alagbon transmission substation would receive power through the Ijora/Alagbon 132kV transmission line.
READ ALSO: Ikeja Electric speaks on planned blackout in parts of Lagos
The statement read, “The Transmission Company of Nigeria plans to carry out maintenance work in Aja substation from Wednesday 7th to Friday 9th September 2022, from 7 am to 7 pm daily. This includes the relocation of Egbin/Aja 330kV Line 3 to a spare Omotosho 330kV Line 2 bay as well as the repair of gas leakage on one of the isolators in the substations.
“During this period, Aja, Lekki transmission stations and the Alagbon/Aja 330kV transmission line would be out of service, to ensure safe workspace for the engineers.
“Similarly, the Alagbon transmission substation would receive power supply through the Ijora/Alagbon 132kV transmission line.
“The maintenance work will affect bulk power supply and expectedly cause an outage in Badore, Sangotedo, Jakande, Chevron, Agungi, Lekki and some parts of Victoria Island.
‘’TCN regrets any inconveniences this may cause electricity consumers within the affected areas and assure Nigerians of its determination to continue to deliver bulk power supply to distribution load centers nationwide.”
Meanwhile, the TCN had about 3 days ago confirmed that a fire incident occurred on Saturday, the 3rd of September at its Adiabo 330/132/33KV substation in Cross River State.
It stated that its engineers were working to ensure the restoration of power supply to the affected areas as they were replacing the affected equipment.
-
Football6 days agoBallon d’Or 2026: Yamal, Mbappe, Kane emerge early favourites
-
Football5 days agoPost-World Cup Shake-Up: Managerial changes, record transfers dominate football headlines
-
Football5 days agoWAFCON 2026: Super Falcons target winning start as Nigeria face debutants Malawi
-
Energy4 days agoNigeria wastes enough gas to Ggenerate 62,400GWh of electricity amid deepening energy crisis — NOSDRA
-
Latest7 days agoAccountability group questions ₦962.8bn Allocation for empowerment projects, official vehicles in 2026 budget
-
Business2 days agoCooking gas dealers slash prices amid intensifying market competition
-
Business1 week agoThe Productivity Puzzle: Why Nigeria’s economy is growing faster than household prosperity
-
Health4 days agoFauci’s personal diaries fuel renewed scrutiny of COVID-19 vaccine safety