Energy
Gas shortage reduces Nigeria’s electricity generation by 20%
Electricity generation companies (GenCos), comprising gas-fired and hydro stations, say they could not generate 1,631.5 megawatts of electricity on Saturday due to unavailability of gas.
This is contained in a daily energy report by the advisory power team, office of the vice-president.
The report said 0 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.
Similarly, it said 3,258.5 megawatts were not generated due to high frequency resulting from unavailability of distribution infrastructure.
The report, however, said the GenCos released an average of 3,349 MegaWatts/hour of electricity into the national grid on Saturday.
It said the electricity sent out by the GenCos was down by 16.77 megawatts from the 3,365 released on Friday.
The report said zero (0) megawatts was recorded as losses due to water management procedures.
The report revealed that the power sector lost an estimated N2.34 billion on Saturday due to insufficient gas supply, distribution and transmission infrastructure.
On sector reform/activities, it said that the dominant constraint for Saturday was high frequency resulting from unavailability of distribution infrastructure.
The report said that the peak generation attained on Saturday was 4,093.4 megawatts.
-
Football4 days agoArgentine presenter Florencia Peña resigns after false on-air report about Lionel Messi’s father
-
Business6 days agoNigeria launches FreeTV digital platform with over 100 free channels
-
Business4 days agoAward-winning Mitsubishi L200 gets anniversary price cut in Nigerian market
-
Comments and Issues1 week agoA tale of two kidnappings
-
Business3 days agoThe CBN’s Exposure Draft on Holding Companies of Banks: Matters Arising
-
Football5 days agoAfrican Teams Show Resilience on FIFA World Cup 2026 Matchday One
-
Latest4 days agoSex video leak sparks disciplinary action as FUOYE suspends two students
-
Latest3 days agoTinubu Grants Customs Boss Adeniyi Final Six-Month Extension to Oversee Single Window Project, Succession